Timeline / Milestones

  • Preparation of engagement plan

    May 2020

     

    -

     

    September 2020

  • Stakeholder Engagement

    October 2020

     

    -

     

    March 2021

    We asked for your views on active travel routes (walking and cycling) in your area and where new routes or improvements are needed
  • Data Analysis and draft map development

    April 2021

     

    -

     

    July 2021

    We analysed all the data and feedback received during the engagement exercise and we used this to develop the draft map
  • Submission of draft maps to Welsh Government for informal approval

    July 2021

     

    -

     

    August 2021

    Welsh Government reviewed draft maps and agreed maps can go to public consultation
  • Statutory Consultation

    August 16th 2021

     

    -

     

    November 7th 2021

    Full 12 week public consultation
  • Submission to Welsh Government

    December 2021

     

    -

     

    December 2021

    Following consideration and analysis of comments received during consultation, making any required amendments where necessary, submission of maps to Welsh Government for final approval